Key Points
- HBC Construction Limited (HBC), formerly Henry Boot Construction, has commenced main construction works on a new cancer centre at Thorpe Park, Leeds, for GenesisCare, the UK’s leading independent cancer care provider.
- The project refurbishes a former office building at 1200 Century Way into a 36,000 sq ft oncology, haematology, and research centre, set to be the largest in GenesisCare’s 16-centre UK network.
- The facility will feature advanced MRI and CT-guided radiotherapy for adaptive, personalised treatments, including two concrete bunkers for Linac systems, MRI, CT, and X-ray scanners.
- Preparatory works, such as soft strip demolition and enabling activities, were completed earlier in 2026 ahead of the main build involving structural alterations, internal fit-out, and landscaping.
- Landscaping includes an elevated first-floor external garden for Systemic Anti-Cancer Therapy patients, plus external services plant, switch room, and sub-station.
- The centre, designed by IDPartnership, is valued at £42 million and marks one of HBC’s first major healthcare projects post-management buyout earlier this year.
- Planning permission was granted in September 2025; the centre is scheduled to open in December 2026, serving patients in the North of England and Scotland who previously travelled to Oxford or London.
- Cushman & Wakefield secured the site for GenesisCare within Scarborough Group’s Thorpe Park development.
- Lee Powell, HBC Managing Director, highlighted the project’s role in enhancing regional cancer services.
- Justin Hely, GenesisCare CEO, confirmed commitment to world-class care and on-track progress.
Leeds (The Leeds Times) March 13, 2026 – HBC Construction Limited has begun main works on a pioneering cancer centre at Thorpe Park, transforming a former office building into GenesisCare’s largest UK facility for advanced oncology treatments.
- Key Points
- What is the HBC Cancer Centre Project in Leeds?
- Who is HBC Construction and Why This Project?
- What Advanced Treatments Will the Centre Offer?
- When Did Planning and Preparatory Works Occur?
- Who Secured the Site and What Role Did They Play?
- What Patient Amenities Are Included?
- What Has GenesisCare Said About the Progress?
- How Will This Impact Northern Cancer Patients?
- What is the Timeline and Value of the Project?
What is the HBC Cancer Centre Project in Leeds?
The development at 1200 Century Way, Thorpe Park, involves refurbishing a disused office into a state-of-the-art 36,000 sq ft centre focused on oncology, haematology, and research, as reported across multiple outlets.
This marks a significant step for GenesisCare, the UK’s pre-eminent independent cancer care provider, expanding its network to include this flagship site. Preparatory phases, including demolition and enabling works, wrapped up earlier this year, paving the way for structural changes and specialist installations.
As detailed by TheBusinessDesk.com, the centre will integrate cutting-edge radiotherapy with both MRI and CT guidance, allowing real-time adaptive treatments personalised to individual cancers.
Place Yorkshire noted the project’s £42 million value and design by IDPartnership, emphasising its role as the network’s largest hub housing two of the world’s most sophisticated radiotherapy systems. GenesisCare’s official site underscores that this will position Leeds among a select global group offering such innovative adaptive radiotherapy.
Who is HBC Construction and Why This Project?
HBC Construction Limited, rebranded from Henry Boot Construction following a management buyout at the start of 2026, secured the contract via a competitive two-stage tender process. This initiative represents one of HBC’s inaugural major healthcare ventures post-buyout, showcasing their expertise in complex refurbishments.
Lee Powell, managing director of HBC, stated to TheBusinessDesk.com:
“We’re proud to be delivering this pioneering oncology, haematology and research centre in Leeds following a successful two-stage tender process.”
He further elaborated:
“The relationship has allowed us to understand the key priorities for GenesisCare and develop an accelerated programme for timely delivery and installation of specialist equipment.”
Powell added:
“With the main works now underway, we’re privileged to be playing our part in enhancing cancer services across the North of England and Scotland. It’s incredibly rewarding to know this facility will make a real difference for patients, giving them access to the latest treatments closer to home. This project reflects HBC’s ongoing commitment to healthcare developments and to supporting local communities through high-quality infrastructure.”
What Advanced Treatments Will the Centre Offer?
The facility will pioneer MRI and CT-guided radiotherapy, enabling highly adaptive therapies tailored precisely to each patient’s cancer profile. Key installations include two bespoke concrete bunkers for Linear Accelerator (Linac) treatment, alongside MRI, CT, and X-ray scanners, as outlined in reports from Place Yorkshire.
According to GenesisCare’s centre page, this setup will revolutionise care by personalising radiotherapy in real-time, establishing the Leeds site as a world leader in adaptive technologies.
TheBusinessDesk.com highlighted its integration into GenesisCare’s UK-wide network, providing northern patients local access to innovations previously requiring travel. Internal refurbishments will support comprehensive oncology and haematology services, complemented by research capabilities.
When Did Planning and Preparatory Works Occur?
Planning approval for the scheme was secured in September 2025, as reported by Healthcare Today on the GenesisCare development. Soft strip demolition and enabling works followed earlier in 2026, setting the stage for main construction commencement in March.
Place Yorkshire, in a piece by Sally Gibson, confirmed these timelines, noting the site’s position within Scarborough Group’s mixed-use Thorpe Park—a commercial and retail hub. TheBusinessDesk.com corroborated that preparatory phases were fully completed prior to the current structural and façade alterations. The project adheres to an accelerated schedule for December 2026 opening.
Who Secured the Site and What Role Did They Play?
Cushman & Wakefield represented GenesisCare in acquiring 1200 Century Way, as credited in Place Yorkshire’s coverage. This transaction embedded the centre within Thorpe Park’s vibrant development by Scarborough Group, blending healthcare with commercial spaces.
What Patient Amenities Are Included?
Beyond clinical facilities, the build incorporates thoughtful landscaping: an elevated first-floor external garden dedicated to patients receiving Systemic Anti-Cancer Therapy (SACT), an external services plant area, switch room, and sub-station. These features prioritise patient wellbeing, offering serene spaces amid treatment, as emphasised in construction updates.
What Has GenesisCare Said About the Progress?
Justin Hely, CEO of GenesisCare, commented to TheBusinessDesk.com:
“GenesisCare is committed to delivering world-class care to people throughout the UK undergoing cancer treatment.”
He continued:
“We continue to make excellent progress at our new centre in Leeds and are on track to bring advanced cancer care to individuals in the North of England and Scotland by the end of this year. We’re looking forward to opening our doors and providing a wide range of diagnostic and cancer care services locally and without delay.”
Place Yorkshire quoted Hely similarly, reinforcing the on-schedule trajectory and regional impact. GenesisCare’s site positions the centre as their 15th (soon 16th) UK outpost, opening in 2026 to serve the North comprehensively.
How Will This Impact Northern Cancer Patients?
Patients from the North of England and Scotland will gain local access to elite treatments, eliminating long journeys to GenesisCare’s Oxford or London sites. As Powell noted to multiple outlets, this enhances services regionally, supporting communities with cutting-edge infrastructure.
Healthcare Today previously reported on the planning win, highlighting the centre’s potential to personalise care via advanced imaging. The project aligns with broader Leeds healthcare advancements, though distinct from NHS facilities like St James’s.
What is the Timeline and Value of the Project?
Valued at £42 million per Place Yorkshire, main works started March 2026 post-preparatory completion, targeting December 2026 opening. Premier Construction News announced the main works initiation, aligning with peer reports.