Key Points
- Contractors have started repair work on Lower Kirkgate, one of Leeds‘ oldest streets, following a partial building collapse on 4 April 2024.
- The road near the Corn Exchange has been closed to traffic since the incident, impacting local businesses.
- Leeds City Council issued an urgent works notice to the property owner, City Fusion, after receiving government approval in December 2024.
- The council has allocated approximately £700,000 for repairs, including £414,500 for a 16-week project by Geo Houlton and Sons, and is seeking to recover costs from the owner.
- Initial safety works were anticipated by late September 2025, but full on-site repairs commenced in March 2026, lasting around 24 weeks total.
- Local business owners have expressed relief, citing reduced footfall over two years.
- Discussions are underway with the West Yorkshire Combined Authority about a potential permanent road closure.
Lower Kirkgate (The Leeds Times) April 18, 2026 – Contractors are now on site at Lower Kirkgate in Leeds city centre, where repair work has finally begun two years after a derelict 18th-century building partially collapsed, closing the historic street to traffic and affecting nearby businesses.
- Key Points
- Why Have Repairs on Lower Kirkgate Taken Two Years to Start?
- What Impact Has the Closure Had on Local Businesses?
- Who Is Responsible for the Repair Costs and Timeline?
- How Was the Urgent Works Notice Issued?
- Background of the Development
- Prediction: How This Development Can Affect Local Businesses and Residents
Why Have Repairs on Lower Kirkgate Taken Two Years to Start?
The partial collapse occurred on 4 April 2024, when a section of an 18th-century structure on Lower Kirkgate caved in, prompting an immediate road closure near the iconic Corn Exchange. Leeds City Council closed the roadway to vehicles as a safety measure, and it has remained inaccessible since.
As reported by the BBC, contractors were initially engaged for repairs following the incident 16 months prior, with safety measures expected by the end of September 2025. A council spokesperson stated,
“With detailed preparations for the work nearing completion, we anticipate that we can begin on-site by the end of September.”
Leeds City Council applied for and received government approval in December 2024 to issue an urgent works notice to the building owners, City Fusion, requiring repairs on the collapsed structure and five adjacent buildings at risk.
ITV News Calendar reported that council bosses ordered the owners to carry out the work or face a £700,000 bill.
Plans advanced in March 2025, when Hello Rayo noted that repairs on the crumbling street could start the following month, 12 months after the collapse. By September 2025, Leeds City Council confirmed that Geo Houlton and Sons had been contracted for a 16-week repair initiative budgeted at £414,500.
Don Mort of Local Democracy Reporting Service, via Hello Rayo, wrote that contractors were hired for urgent repairs on the historic street.
The BBC further detailed in March 2026 that renovation efforts had commenced after two years of closure, with the council coordinating the work. A council representative confirmed,
“We can verify that our contractors have commenced work on-site.”
They added that more updates on progress would be provided “in due course” and thanked residents and businesses for their patience.
Hello, Rayo reported in March 2026 that repairs started after the urgent works notice allowed the council to proceed and recover costs.
The council stated that initial works would take about six weeks, followed by further repairs lasting around 18 weeks.
What Impact Has the Closure Had on Local Businesses?
Local business owners have highlighted significant challenges due to the prolonged closure. Hello, Rayo quoted one business operator near the Corn Exchange who said,
“The footfall will come back once this has re-opened. But the last two years has been dire for the businesses on the street. It’s been pretty rough.”
The BBC noted that business owners impacted by reduced footfall expressed relief at the start of repairs. Lower Kirkgate, once part of a city centre bus route, has seen declining trade since April 2024.
Martin Hamilton, director of a local trust, mentioned in a statement last month that talks would begin with the West Yorkshire Combined Authority on the possibility of a permanent road closure.
The building owner, City Fusion, has been approached for comment, but no response was noted in the reports.
Who Is Responsible for the Repair Costs and Timeline?
Leeds City Council has funded the urgent repairs with around £700,000, including the £414,500 contract with Geo Houlton and Sons. The authority is attempting to recoup these costs from the property owner.
The repair initiative is set to last 24 weeks in total, with initial phases focusing on safety and stabilisation. A restricted area will manage site safety once the exact schedule is set, as per the council’s September 2025 announcement.
Earlier projections included a 16-week timeline from September 2025, but work commenced later in March 2026.
How Was the Urgent Works Notice Issued?
In December 2024, Leeds City Council received permission from the government to serve the notice on City Fusion, targeting the collapsed building and five others at risk. This legal step enabled the council to undertake the repairs and bill the owners.
The derelict property’s partial fall in April 2024 necessitated the action, with part of the road closed since.
Background of the Development
Lower Kirkgate is one of Leeds’ oldest thoroughfares, featuring 18th-century structures near the Corn Exchange. The partial collapse on 4 April 2024 involved a derelict building, leading to immediate traffic restrictions.
Legal notices followed, culminating in the December 2024 urgent works approval. Preparations spanned 2025, with contractor hiring in September and works starting in March 2026. The council’s involvement stems from public safety obligations, with cost recovery efforts ongoing.
Prediction: How This Development Can Affect Local Businesses and Residents
The repair work on Lower Kirkgate can restore vehicle and pedestrian access after two years, potentially increasing footfall for nearby businesses that have faced reduced trade. Reopening the street near the Corn Exchange may revive its role as a city centre route, benefiting operators who described the period as “dire.” Initial six-week works and subsequent 18-week repairs could mean disruptions during construction, requiring managed restricted areas.
If costs are recovered from the owner, council resources may remain available for other maintenance. Talks on permanent closure with the West Yorkshire Combined Authority could alter traffic patterns long-term. Residents and visitors may regain access to the historic area, supporting local trade recovery.